Backward planning
We date every milestone back from the completion deadline and build in slack where the risk sits: grid approval, weather and equipment.
A delivery route for projects with a fixed spend deadline. We plan the programme backwards from the date, run surveys, design and grid applications side by side, and put our own crews on site, so the money is spent, the system is commissioned and the evidence is ready on time.
This page is for programme managers, estates leads and finance officers with a grant award and a completion date that is closer than it looks. Funding often arrives late in the year, with procurement still to run and winter ahead. The projects that finish on time are the ones planned backwards from the deadline on day one.
Fast Track Delivery is how we do that. We map every milestone from award to commissioning, pick out the long-lead items such as DNO applications, structural surveys and equipment, and start them all straight away. Our engineering, roofing and installation teams are in-house, so we control our own capacity instead of waiting for someone else’s.
Along the way, you get milestone reports you can pass straight to the funder. At the end, you get the certificates, monitoring and evidence your funder return needs.
We date every milestone back from the completion deadline and build in slack where the risk sits: grid approval, weather and equipment.
DNO applications, structural surveys, design and procurement paperwork run at the same time, not one after another.
Our own engineers, electricians and roofers are scheduled by us, so your programme is not left waiting on other firms.
We secure panels, inverters, batteries, steelwork and chargers early, so site work is never held up waiting for a delivery.
Weekly progress against the programme, in a format you can forward to the funder as it is.
Quotations, certificates and evidence prepared the way your funder return expects them.
Visit the Funding HubWe book surveys within days of instruction and start long-lead items straight away.
Grant-funded programme experienceEngineering, roofing, installation and O&M are all in-house, so no time is lost in hand-offs.
Single point of contactAccreditations, insurances, RAMS and policies ready for whichever route your funding requires.
MCS · CHAS · ConstructionlineCommissioning, certificates and monitoring arrive with the finished works, not months later.
Funder return readyWe map the award date, completion date and every milestone in between in the first week.
Week oneThe DNO application, surveys, design and procurement documents all start together.
ImmediatelyWe order long-lead items and lock delivery dates into the programme.
No waitingOur own crews work on site in the agreed windows, around your operations and the weather plan.
In-house capacityTesting, certificates, monitoring and the funder evidence pack, all handed over together.
On the dateShare your award, deadline and site details. A UK engineer will plan the programme back from the date and tell you honestly whether it can be met.
We typically book surveys within days of instruction, and long-lead items such as the DNO application start straight away.
Grid approvals, structural surveys and equipment lead times. Fast Track Delivery starts all three together on day one.
Yes. The first-week programme shows what is achievable. If a date is not realistic, we say so and help you agree a revised milestone with the funder early on.
Yes. We phase programmes across sites, schedule our own crews and report site by site.
Milestone reports during delivery, then MCS certificates, electrical certificates, DNO confirmation, monitoring access and as-built information at completion.
No. Every project follows the same RAMS, MCS certification, electrical testing and commissioning. Time is saved by running tasks in parallel and starting long-lead items early, not by skipping steps.
DNO timescales are outside any installer’s control, which is why we submit on day one. If approval looks likely to affect your deadline, we tell you straight away and set out the options, such as phasing the work, so you can speak to the funder early.
A free feasibility study and a backwards-planned programme from our UK engineering team.